KIZOMBA A FPSO Installation – 1400M Water Depth

Location: Engineering in Houston, Offshore Installation in Angola
Duration: July 2003 – June 2004
Project Scope:
  • Project Management
  • Mooring System Design
  • Installation Equipment Specification and Procedure Development
  • Managed all deck operations for mooring hook-up and tensioning

ATLANTIS Production Semi-Submersible Riser Installation – 2150m Water Depth

Location: Engineering in Houston, Offshore Installation in Gulf of Mexico
Duration: May 2005 – Present
Project Scope:
  • Installation, assembly of the SCR Pull-in 1250 Ts chain jack system
  • Managed all Riser Pull-in Operations 2150M Water depth
  • BP representative for review of field development pipelaying
    (J-Lay) operations procedures
  • BP representative for all hook-up operations

Armada Perkasa FPSO Installation – 13m Water Depth

Location: Engineering in Singapore, Offshore Installation in Nigeria
Duration: August 2007 – August 2008
Project Scope:
  • EPIC Installation Contract
  • Installation Engineering
  • Deck Pull-in Equipment Preparation
  • Supply of Chartered Marine Spread

KIZOMBA B FPSO Installation – 1400M Water Depth

Location: Engineering in Houston, Offshore Installation in Angola
Duration: July 2003 – June 2004
Project Scope:
  • Project Management
  • Mooring System Design
  • Installation Equipment Specification
  • Installation Procedure Development
  • Managed all deck operations for mooring hook-up and tensioning

TECHNIP Consultancy Support Services

Location: PMT Support in Houston, Site Locations in China
Duration: January 2012 – Present
Project Scope:
  • Offshore Business Unit’s Project Support and Consultation Service:
    • Solwara 1 Mining Vessel, mooring feasibility study
    • Solawara 1 Mining Vessel, equipment package delivery
    • Aasta Hansteen Spar

BP Thunderhorse Chain Jack Repair – 1920m Water Depth

Location: Engineering in Houston, Offshore Repair in Gulf of Mexico
Duration: June 2012 – Present
Project Scope:
  • Constructability Review for Chain Jack Cross Arm Replacement
  • Repair Execution Engineering
  • Design of Load Handling Equipment

OYO – Armada Perdana FPSO Installation – 425m Water Depth

Location: Engineering in Singapore, Offshore Installation in Nigeria
Duration: August 2008 – November 2009
Project Scope:
  • Installation Engineering
  • Delivery of Installation: 150t A-Frame and 200t Reel Drive System
  • Supply of ROV System
  • Conversion of a mid-sized AHTS to a subsea construction vessel
  • Deck Equipment Preparation
  • Offshore Mooring Pre-Set Installation
  • FPSO Mooring Hook-Up and Positioning
  • Riser Hook-Up – Pull in operations

Delivery of Mooring Equipment – Early Production Vessel

Location: Engineering & PMT in Houston, Fabrication in China
Duration: April 2012 – January 2013
Project Scope:
  • Design and delivery of deck mooring equipment to include
    • Qty 2 – 150 ton Deck Pull-In Winches and control consoles
    • Winch HPU unit
    • 50 ton Deck Winch

Xikomba FPSO Disconnect – 1310M Water Depth

Location: Offshore Disconnect in Angola
Duration: June 2011 – July 2011
Project Scope:
  • Project Management Client Representation
  • Installation Procedure Review and Approval
  • Offshore Installation Management

RATU Songkhla FSO Installation – 50M Water Depth

Location: Engineering in Singapore, Offshore Installation in Malaysia
Duration: May 2009 – August 2009
Project Scope:
  • Project Management Client Representation
  • Installation Procedure Review and Approval
  • Offshore Installation Management

MAD DOG SPAR Installation – 1400M Water Depth

Location: Engineering in Houston, Offshore Installation in Gulf of Mexico
Duration: July 2001 – Oct 2003
Project Scope:
  • Installation, Assembly and Operation
    of the 1250Ts SCR pull in chain jack system

CAT Intervention Tower

Location: Engineering and Fabrication in Singapore,
Offshore testing and operations in Malaysia
Duration: March 2011 – August 2011
Project Scope:
  • FEED Study Engineering for fit to purpose tower
  • Structural Analysis
  • Engineering Drawings
  • Tower Fabrication works
  • Hydraulic Heave Compensator System
  • Control System and sensors
  • Offshore testing / operation
  • Operations and maintenance manuals

SPM3 CALM Buoy Repair – 50M Water Depth

Location: Engineering in Singapore, Offshore Installation in Nigeria
Duration: Dec 2008 – August 2009
Project Scope:
  • Mooring Analysis
  • Repair Engineering & Procedures
  • Offshore mooring and floating hose repair and adjustment
  • CALM Buoy system placed back into operation